2.

In order for JIT purchasing to be truly effective, which of the following factors need to be
in place?
I. The supplier base needs to be reduced.
II. Single source suppliers need to be used.
III. The supplier must be willing to hold the inventory.
IV. The schedule needs to have some stability.

Multiple choice question Taken: 30 Correct: 60% (18) Wrong: 40% (12) Skipped: 0% (0)

I , II & III

3% (1)

I, II & IV

60% (18)

II, III & IV

20% (6)

I, II, III & IV

17% (5)
Multiple answers Random order Simple scoring
3.

Which statement is true about the objectives of inventory management?

Multiple choice question Taken: 29 Correct: 10% (3) Wrong: 90% (26) Skipped: 0% (0)

Minimize customer service, maximize inventory investment, maximize productivity

0% (0)

Maximize customer service, maximize inventory investment, maximize productivity

10% (3)

Maximize customer service, minimize inventory investment, maximize productivity

90% (26)

None of the above

0% (0)
Multiple answers Random order Simple scoring
4. Company A's purchasing department has been negotiating with a vendor for product 123. The vendor has suggested the company commit to 20% of the vendor's output over the next six months. This practice is known as:
Multiple choice question Taken: 29 Correct: 38% (11) Wrong: 62% (18) Skipped: 0% (0)
long-term contracting. 10% (3)
capacity buying. 38% (11)
capacity buying. 52% (15)
None of the above 0% (0)
Multiple answers Random order Simple scoring
5. The field service technicians order replacement parts for repair purposes. This is an example of:
Multiple choice question Taken: 29 Correct: 93% (27) Wrong: 7% (2) Skipped: 0% (0)
dependent demand. 3% (1)
economic ordering quantity. 0% (0)
a reorder point procedure. 3% (1)
independent demand 93% (27)
Multiple answers Random order Simple scoring
6.

Providing suppliers with an MRP planning report allows the suppliers to do which of the
following?
I. Reduce the cost of raw materials
II. Schedule their plants more efficiently
III. Stabilize their workforce

Multiple choice question Taken: 29 Correct: 79% (23) Wrong: 21% (6) Skipped: 0% (0)

I & II

3% (1)

I & III

0% (0)
II & III 17% (5)
I, II & III 79% (23)
Multiple answers Random order Simple scoring
7. When the MRP reports are provided to suppliers for use in their planning, the planned orders from those reports become the supplier's:
Multiple choice question Taken: 28 Correct: 93% (26) Wrong: 7% (2) Skipped: 0% (0)
planned orders. 4% (1)
gross requirements. 93% (26)
scheduled receipts. 4% (1)
net requirements. 0% (0)
Multiple answers Random order Simple scoring
8. The automatic updating of scheduled receipts by the computer should be used when:
Multiple choice question Taken: 28 Correct: 86% (24) Wrong: 14% (4) Skipped: 0% (0)
the system just starts up. 4% (1)
new planners are hired. 0% (0)
the system is maintained properly. 86% (24)
Just-in-Time has been implemented. 11% (3)
Multiple answers Random order Simple scoring
9. The major benefit for a supplier to develop a strategic alliance with a customer is:
Multiple choice question Taken: 28 Correct: 89% (25) Wrong: 11% (3) Skipped: 0% (0)
free access to engineers at the customer. 4% (1)
long term contracts. 89% (25)
more profitable sales. 7% (2)
supplier awards. 0% (0)
Multiple answers Random order Simple scoring
10.

Often, companies will use cross-functional teams to develop new designs and get products to market. These cross-functional teams will very often include the appropriate suppliers in the design. This allows the product development activities to overlap each other, thereby, shortening the product development time. This process of overlapping activities in the product development cycle is called:

Multiple choice question Taken: 28 Correct: 93% (26) Wrong: 7% (2) Skipped: 0% (0)

design for quality.

7% (2)

design accountability.

0% (0)

supplier partnerships.

0% (0)

concurrent engineering.

93% (26)
Multiple answers Random order Simple scoring
11. A disciplined effort to compare the function performed by an item and its cost in an attempt to find a lower cost alternative is called:
Multiple choice question Taken: 28 Correct: 93% (26) Wrong: 7% (2) Skipped: 0% (0)
item evaluation. 7% (2)
re-engineering. 0% (0)
supplier partnership. 0% (0)
value analysis. 93% (26)
Multiple answers Random order Simple scoring
12. The process of supplier evaluation rates suppliers on their ability to meet price targets, quality specifications, and:
Multiple choice question Taken: 27 Correct: 85% (23) Wrong: 15% (4) Skipped: 0% (0)
order quotes. 11% (3)
service calls. 0% (0)
delivery dates. 85% (23)
capacity levels. 4% (1)
Multiple answers Random order Simple scoring
13.

It is important to maintain a close relationship with certified supplier partners. The most difficult part of establishing a supplier partnership is:

Multiple choice question Taken: 27 Correct: 85% (23) Wrong: 15% (4) Skipped: 0% (0)
establishing trust in the relationship. 85% (23)
developing a consistent, accurate form of communication. 11% (3)
ensuring consistent meetings are occurring to build relationships across company boundaries. 0% (0)
training and educating the workforce 4% (1)
Multiple answers Random order Simple scoring
14. In recent years, many companies have become assemblers of their products where in the past they may have manufactured many of the subassemblies, as well. This trend towards having many large sections of the product assembled outside the manufacturer's primary operation is called:
Multiple choice question Taken: 27 Correct: 100% (27) Wrong: 0% (0) Skipped: 0% (0)
capacity buying. 0% (0)
global sourcing. 0% (0)
outsourcing. 100% (27)
international sourcing. 0% (0)
Multiple answers Random order Simple scoring
15.

When a supplier has been certified and has been reliably delivering products to a company, often times the company will develop a process, whereby, purchase orders are no longer necessary. The product will arrive at the dock, bypass inspection and counting, and be delivered to the production line. This delivery location on the production line is called a:

Multiple choice question Taken: 27 Correct: 81% (22) Wrong: 19% (5) Skipped: 0% (0)

point of use location.

81% (22)

consignment location.

0% (0)

dock to stock location.

15% (4)

VMI location.

4% (1)
Multiple answers Random order Simple scoring
16.

Sometimes, a supplier will consign inventory to a location on the production line of the customer. The customer will then use the product and pay for the materials used each week. This method of inventory management is called:

Multiple choice question Taken: 27 Correct: 100% (27) Wrong: 0% (0) Skipped: 0% (0)
receipt routing. 0% (0)
paypoint. 0% (0)
receipt and pay. 0% (0)
pay on use. 100% (27)
Multiple answers Random order Simple scoring
17.

The mission of the purchasing department is to identify and qualify adequate sources of competitively priced supply to manufacture the products required by the marketplace. Many times, this mission includes identifying sources regardless of their location. This is called:

Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)

faceted sourcing.

7% (2)

global sourcing.

93% (25)

localized sourcing.

0% (0)
leveled sourcing. 0% (0)
Multiple answers Random order Simple scoring
18.

In order for a supplier to supply in a JIT manner, meeting the schedule with the right products at the right time, which of the following is imperative?

Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 0% (0)
Solid MRP system 19% (5)
Stable schedule 74% (20)
Flexible suppliers 4% (1)
Extra capacity 4% (1)
Multiple answers Random order Simple scoring
19. One solution to minimize costs when getting small frequent deliveries from suppliers would be to utilize backhauling. Which of the following best defines backhauling?
Multiple choice question Taken: 27 Correct: 100% (27) Wrong: 0% (0) Skipped: 0% (0)
FOB at the suppliers dock 0% (0)
Using a full truck outbound and an LTL load inbound 0% (0)
Using Kanban to signal suppliers for delivery 0% (0)
Utilizing your trucks to pick up product at suppliers on the way back to your facility 100% (27)
Multiple answers Random order Simple scoring
20. Sometimes, the more distant suppliers will absorb the additional freight charge to match the freight charge of the geographically closer supplier. This practice is known as:
Multiple choice question Taken: 27 Correct: 81% (22) Wrong: 19% (5) Skipped: 0% (0)
freight equalization. 81% (22)
freight consolidation. 15% (4)
freight dissemination. 4% (1)
freight socialization. 0% (0)
Multiple answers Random order Simple scoring
21. A supplier who consistently meets predetermined quality, cost, delivery, financial, and quantity objectives will generally be awarded:
Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)
more purchase orders. 11% (3)
a plaque. 0% (0)
supplier of the year. 0% (0)
certified status. 89% (24)
Multiple answers Random order Simple scoring
22. A company has short product life cycles and consequently, experiences significant obsolete inventory write-offs annually. Of the following methods, which of the following would not be an effective handling of the obsolescence
Multiple choice question Taken: 27 Correct: 78% (21) Wrong: 22% (6) Skipped: 0% (0)
Write off an equal amount of the estimated annual obsolete inventory each month 11% (3)
Maximize profits in the current year by waiting to write off obsolete inventory until the next year 78% (21)
Write off the obsolete inventory and dispose of the parts as they are identified 11% (3)
Write off obsolete inventory as soon as it is identified 0% (0)
Multiple answers Random order Simple scoring
23. Which of the following is not included by planning factors using the item master record?
Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 0% (0)
On hand balance 74% (20)
Safety stock 11% (3)
Lot sizing rules 11% (3)
Lead time 4% (1)
Multiple answers Random order Simple scoring
24.

Standard costs are generally established before actual production in a standard cost system. Using this system, how would management determine how well goals are achieved by production?

Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)
Machine utilization above 90% 4% (1)
High productivity per man hour 7% (2)
Favorable variances from standard cost 89% (24)
Low defects per 1,000 0% (0)
Multiple answers Random order Simple scoring
25. A company has an annual requirement of 2,000 units for a part. How many exposures does this company have if it places orders in the quantity of 400 and maintains a safety stock of 0?
Multiple choice question Taken: 27 Correct: 100% (27) Wrong: 0% (0) Skipped: 0% (0)
10 0% (0)
5 100% (27)
20 0% (0)
None 0% (0)
Multiple answers Random order Simple scoring
26.

The Indoor Store presents the following facts pertaining to the cost of one product carried in its merchandise inventory:
Beginning inventory on hand, 200 units @ $15 = $3,000
Purchase June 1, 200 units @$16 = $3,200
Purchase July 5, 200 units @ $20 = $4,000
Purchase August 25, 200 units @ $25 = $5,000
A new order comes in for 500 units.  What is the cost of goods sold that should be recorded using a simple weighted average using the LIFO methodology?

Multiple choice question Taken: 27 Correct: 96% (26) Wrong: 4% (1) Skipped: 0% (0)
$10,600 96% (26)
$9,200 0% (0)
$11,100 4% (1)
$10,100 0% (0)
Multiple answers Random order Simple scoring
27. All of the following are techniques to reduce lead time EXCEPT
Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)
Overlapping 0% (0)
Order Splitting 4% (1)
Operation Splitting 7% (2)
Renegotiate supplier terms 89% (24)
Multiple answers Random order Simple scoring
28.

Which of the following are basic process flow scheduling approaches?
I.  Vendor Dominated Scheduling (VDS)
II.  Processor-Dominated Scheduling (PDS)
III. Material-Dominated Scheduling (MDS)

Multiple choice question Taken: 27 Correct: 78% (21) Wrong: 22% (6) Skipped: 0% (0)

I & II

11% (3)

II & III

78% (21)
I & III 4% (1)
I, II & III 7% (2)
Multiple answers Random order Simple scoring
29. Today- what is NOT a major issue with supplier partnerships?
Multiple choice question Taken: 27 Correct: 70% (19) Wrong: 30% (8) Skipped: 0% (0)
Delivery Performance 4% (1)
Price 70% (19)
Responsiveness 19% (5)
Quality 7% (2)
Multiple answers Random order Simple scoring
30. Total Inventory minus Productive Inventory minus protective Inventory equals what?
Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)
Excess Inventory 93% (25)
Obsolete Inventory 4% (1)
Semi Finished goods inventory 0% (0)
Finished goods inventory 4% (1)
Multiple answers Random order Simple scoring
31.

During an inflationary period, which of the following would NOT be associated with LIFO inventory valuation?
I.  Increase Cost of Goods Sold
II. Decrease Cash Flow
III.  Increase Profits

Multiple choice question Taken: 27 Correct: 56% (15) Wrong: 44% (12) Skipped: 0% (0)

I

15% (4)

II

19% (5)
II & III 56% (15)
I & III 11% (3)
Multiple answers Random order Simple scoring
32.

All of the following ensures capacity availability matches demand in the following areas EXCEPT

Multiple choice question Taken: 27 Correct: 59% (16) Wrong: 41% (11) Skipped: 0% (0)

Final Assembly Schedule

11% (3)

Master Planning

4% (1)

Work Center

26% (7)

Inventory

59% (16)
Multiple answers Random order Simple scoring
33. What equals direct time charged/ clock time scheduled?
Multiple choice question Taken: 27 Correct: 70% (19) Wrong: 30% (8) Skipped: 0% (0)
Theoretical Capacity 7% (2)
Efficiency 22% (6)
Utilization 70% (19)
Demonstrated Capacity 0% (0)
Multiple answers Random order Simple scoring
34.

Although the primary role of the MRP system is often assumed to be balancing supply and demand through the time phased netting process, which of the following is the other major function of MRP?

Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 0% (0)
Maintain valid due dates for all open orders 74% (20)
As order due dates change, recalculate the forecasts 4% (1)
Move the orders for which there is no capacity 4% (1)
Provide messages regarding the scheduled receipts 19% (5)
Multiple answers Random order Simple scoring
35. The acceptable tolerance of error associated with physical inventory is generally limited to which of the following?
Multiple choice question Taken: 27 Correct: 78% (21) Wrong: 22% (6) Skipped: 0% (0)
One percent of the inventory value 4% (1)
It is dependent on the company and its controls 78% (21)
It is independent from the company and its controls 7% (2)
No acceptable write-off exists in association with a physical inventory 11% (3)
Multiple answers Random order Simple scoring
36. Which of the following definitions best matches the term "equal runout quantities"?
Multiple choice question Taken: 27 Correct: 70% (19) Wrong: 30% (8) Skipped: 0% (0)
The date for obsolete inventory must be gone 0% (0)
Product is due date for being out of stock 7% (2)
"Use up before change" feature in the engineering change order 22% (6)
Order quantities of group items which will be depleted at the same time 70% (19)
Multiple answers Random order Simple scoring
37.

Some industries have inventory carrying costs as high as 40%, sometimes they are even higher. Which of the following items is not included in calculating the carrying cost?

Multiple choice question Taken: 27 Correct: 96% (26) Wrong: 4% (1) Skipped: 0% (0)

Cost of capital

0% (0)

Taxes and insurance on the inventory

4% (1)

Warehousing labor

0% (0)

Manufacturing overtime

96% (26)
Multiple answers Random order Simple scoring
38. Which of the following is not an input from another system required by Capacity Requirements Planning?
Multiple choice question Taken: 27 Correct: 52% (14) Wrong: 48% (13) Skipped: 0% (0)
Resource plan 52% (14)
Routings 0% (0)
All of the choices are required inputs 30% (8)
Work-in-process inventory 19% (5)
Multiple answers Random order Simple scoring
39. On what should emphasis be placed if the priority system is to be effective?
Multiple choice question Taken: 27 Correct: 70% (19) Wrong: 30% (8) Skipped: 0% (0)
Using order completion percentages 0% (0)
Maintenance of valid due dates 70% (19)
Using hot lists to change due dates 0% (0)
Meeting due dates 30% (8)
Multiple answers Random order Simple scoring
40. Which of the following demand patterns works most effectively with a reorder point system?
Multiple choice question Taken: 27 Correct: 96% (26) Wrong: 4% (1) Skipped: 0% (0)
A lumpy demand pattern 0% (0)
A smooth, consistent pattern 96% (26)
A seasonal demand pattern 0% (0)
A sawtooth pattern 4% (1)
Multiple answers Random order Simple scoring
41.

It is acceptable to manage obsolete inventory in which of the following ways?
I. Holding write-offs until after year end to keep profits up
II. Accruing the same write-off each month to smooth the financial impact

Multiple choice question Taken: 27 Correct: 81% (22) Wrong: 19% (5) Skipped: 0% (0)

I Only

7% (2)

II Only

81% (22)
Both I & II should be used 11% (3)
Either I or II should be used 0% (0)
Multiple answers Random order Simple scoring
42. Which of the following is false regarding the lotfor- lot technique when used in an MRP environment?
Multiple choice question Taken: 27 Correct: 81% (22) Wrong: 19% (5) Skipped: 0% (0)
The least inventory is created 0% (0)
No residual inventory will be ordered 15% (4)
Residual inventory will exist 81% (22)
Only net requirements will be ordered 4% (1)
Multiple answers Random order Simple scoring
43.

Which of the following is a true statement concerning the fixed order quantity system?

I. An order is placed when the reorder point is reached by on hand balance
II. The order interval varies
III. Quantity for each order varies widely

Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)

I

11% (3)

II

89% (24)
I & III 0% (0)
II & III 0% (0)
Multiple answers Random order Simple scoring
44. A statistical order point system would be best applied in which of the following company environments?
Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)
An erratic demand pattern exists 7% (2)
Stock components are assembled to a customer order 0% (0)
Orders are filled from inventory 93% (25)
Production occurs only after receiving a customer order 0% (0)
Multiple answers Random order Simple scoring
45. What is the order process when using a min-max inventory system?
Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)
Order up to the maximum when the minimum is reached 93% (25)
Order the maximum when the minimum is reached 7% (2)
Order the minimum when the maximum is reached 0% (0)
None of the choices reflect the correct process 0% (0)
Multiple answers Random order Simple scoring
46.

Which of the following is attributed to a useful load projection?

I. It is based on priorities which are valid
II. The load on the factory is complete
III. It provides visibility into the future

Multiple choice question Taken: 27 Correct: 67% (18) Wrong: 33% (9) Skipped: 0% (0)

I & II

0% (0)

I & III

30% (8)

II & III

4% (1)

I, II & III

67% (18)
Multiple answers Random order Simple scoring
47.

Using the data below, determine the reorder
point.
On hand balance = 200
Weekly usage = 200
Leadtime = 3w
Safety stock = 100
 

Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)

700

93% (25)

600

4% (1)
800 4% (1)
550 0% (0)
Multiple answers Random order Simple scoring
48. Which reason below has the most impact on the need for inventory record accuracy?
Multiple choice question Taken: 27 Correct: 19% (5) Wrong: 81% (22) Skipped: 0% (0)
People develop increased faith in the “system” 4% (1)
Auditors allow elimination of the physical inventory 19% (5)
The MRP system erroneously plans without accuracy 70% (19)
None of the reasons above would necessitate inventory record accuracy 7% (2)
Multiple answers Random order Simple scoring
49.

Which of the following choices reflects a pair of requirements necessary to calculate safety stock?
I. Customer service level needed and annual demand for the part
II.  Actual versus forecast differences and annual demand for the part
III.  Customer service level needed and actual versus forecast difference

Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 0% (0)

I & III

7% (2)

II & III

19% (5)
II Only 0% (0)
III Only 74% (20)
Multiple answers Random order Simple scoring
50. The need for expediting can be minimized by which of the following?
Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)
Placing orders with enough leadtime 89% (24)
A real time ERP system 4% (1)
Kanban signaling 4% (1)
Electronic Data Interchange 4% (1)
Multiple answers Random order Simple scoring
51. All of the following are objectives of cycle counting EXCEPT
Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)
Detect significant errors 4% (1)
Find and fix causes 4% (1)
Control the record accuracy 0% (0)
Maintain yearly physical inventory 93% (25)
Multiple answers Random order Simple scoring
52.

Michelle's diaper company is trying to determine the Target Inventory Level for their best selling diapers.  With the following information, what is the target inventory level?
Lead time = 2 weeks
Forecast = 40 per week
Review period = 4 weeks
Safety Stock = 50

Multiple choice question Taken: 27 Correct: 70% (19) Wrong: 30% (8) Skipped: 0% (0)

210

19% (5)

290

70% (19)

170

0% (0)

130

11% (3)
Multiple answers Random order Simple scoring
53. Which of the following would NOT be included in top management planning?
Multiple choice question Taken: 27 Correct: 78% (21) Wrong: 22% (6) Skipped: 0% (0)
Business Planning 0% (0)
Distribution Planning 78% (21)
Sales and Operations Planning 4% (1)
Resource Requirements Planning 19% (5)
Multiple answers Random order Simple scoring
54.

What are the ways to measure variation in demand
I.   Standard Deviation
II.  Factor Deviation
III. Mean Absolute Deviation

Multiple choice question Taken: 27 Correct: 93% (25) Wrong: 7% (2) Skipped: 0% (0)

I & II

4% (1)

I & III

93% (25)

II & III

0% (0)

I, II & III

4% (1)
Multiple answers Random order Simple scoring
55.

Actual lead time is directly affected by what?

Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 0% (0)

Capacity Available

74% (20)

MPS Schedule

19% (5)

Customer Order Rate

0% (0)

MRP

7% (2)
Multiple answers Random order Simple scoring
56.

What are the three areas of simulation?
I.  Lot Order Sizing
II.  MRP as a simulator
III.  "What If" Facility
IV.  Linear Programming

Multiple choice question Taken: 27 Correct: 56% (15) Wrong: 44% (12) Skipped: 0% (0)

I, II & III

30% (8)

II, III & IV

56% (15)

III, IV & I

7% (2)

I, II, III & IV

7% (2)
Multiple answers Random order Simple scoring
57.

Holding Costs Include all of the following EXCEPT

Multiple choice question Taken: 27 Correct: 96% (26) Wrong: 4% (1) Skipped: 0% (0)
Pilferage and Spoilage 4% (1)

Ram materials

96% (26)
Obsolescence and Determination 0% (0)
Storage and Handling 0% (0)
Multiple answers Random order Simple scoring
58.

What is defined as the amount of planned work scheduled for and actual work released to a facility, work center, or operation for a specific span of time?

Multiple choice question Taken: 27 Correct: 100% (27) Wrong: 0% (0) Skipped: 0% (0)
Volume 0% (0)

Load

100% (27)
Capacity 0% (0)
Mix 0% (0)
Multiple answers Random order Simple scoring
59.

A purchase order is signed with ABC company for $3,000 worth of materials.  The average salary of a buyer is paid $25 an hour and manufacturing gets paid $20 an hour.
It takes 5 hours for a buyer to set up a purchase order and it takes manufacturing 10 hours to set up the job and 40 hours to process the job
How much are the ordering/ setup costs for this purchase order

Multiple choice question Taken: 27 Correct: 67% (18) Wrong: 33% (9) Skipped: 0% (0)

325

67% (18)

1125

15% (4)
125 15% (4)
825 4% (1)
Multiple answers Random order Simple scoring
60. For a make to stock environment, when the part has passed final inspection and booked to stores it becomes what?
Multiple choice question Taken: 27 Correct: 89% (24) Wrong: 11% (3) Skipped: 0% (0)

Raw material inventory

7% (2)
Semi finished goods inventory 4% (1)
Finished goods inventory 89% (24)
MRO Inventory 0% (0)
Multiple answers Random order Simple scoring
61.

The difference between Projected Available Balance and Projected On-Hand Balance is that Projected On-Hand Balance what?

Multiple choice question Taken: 27 Correct: 74% (20) Wrong: 26% (7) Skipped: 4% (1)

Excludes planned orders

74% (20)

Include planned orders

4% (1)

Excludes forecast orders

19% (5)

Includes forecast orders

0% (0)
Multiple answers Random order Simple scoring

Please Log in or Register  or BUY to view/update this article.

Sponsered Links

X
Loading